The contractor finishing the pavement on Highway E (12th Street) following the installation of the new water main will be back on site the week of July 20.
They will start with curb and driveway prep work at the start of the week before installing new curb by the middle of that week.
Pavement work will start the following week. It will start with milling the current surface before new asphalt is laid down.
Landscaping will follow and take about a week.